Construction - root cellar outside vents done1 crop Nov. 2022.jpg

The contractor arrived just before 3PM and went to work enlarging the 6” holes so the pipes would go in. Then he and I cut pipes and glued them together.

We discovered that the 6” 45° elbows I’d finally found have a 6¾” I.D. and are far too big to use. I will have to return them.

As we were assembling what we did have, it slipped sideways and we realized we could leave it like that and not bother with 45° elbows on the outside.

Construction - root cellar outside vents done2 crop Nov. 2022.jpg

So they will lean like this.

I now have to find another 90° elbow and (2) 45° elbows to finish the work inside. That will have to wait until Monday, when I find out about returning the too big ones.